Quantifying the Impact of Work Environment Factors on the Variability of Labour Productivity in Wall Plastering
Loading...
Date
Journal Title
Journal ISSN
Volume Title
Publisher
Journal of Construction in Developing Countries
DOI
Abstract
Abstract: Variability in labour productivity is a performance inhibitor and a determinant of
effective and ineffective projects. It has hampered the intercomparison of construction projects
and the accurate forecasting of project duration and cost. This study chose wall plastering
activities as a case study. This study aims to quantify the impact of work environment factors
on the variability of labour productivity. Data were collected using direct site observations and
structured questionnaires. The results revealed that “Waiting for materials” (62.4%), “Being on
the job but not working” (52.6%) and “Work area congestion” (52.5%) all had negative effects
on labour productivity variance. Other negative factors include “Rework” (51.7%), “Waiting
for tools/equipment” (51.1%), “Waiting for information” (47.2%) and “Weather changes”. The
overall average daily productivity was 1.268 whr/m2, baseline productivity = 0.993 whr/m2 and
variation in daily productivity = 22.08%; where whr refers to work hours. The findings identified
significant work environment factors and quantified their impacts on labour productivity
variability in plastering activity. The results indicate that work environment factors during work
in progress significantly impact the variability of labour productivity in plastering work and
ample consideration should be given to its effects.
Description
Citation
Agbo, Izam and Ayegba (2022)