A post-contract project analysis of material waste and cost overrun on construction sites in Abuja, Nigeria
Loading...
Date
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
Acta Structilia 2017
DOI
Abstract
Material waste and cost overrun have
been identified as common problems in the
construction industry. These problems occur
at both pre- and post-contract stages of a
construction project. As a result of a dearth of
empirical research and low level of awareness,
the majority of managers of construction
projects in Nigeria pay hardly any attention to
material waste issues that affect cost overrun.
This article examines the material waste issues
that affect cost overruns at the post-contract
stage of building projects.
The study covers building construction projects
in Abuja, Nigeria. In-depth interviews were
conducted with professionals using purposive
sampling technique. It is purposive, because
only building professionals handling projects that
are worth over eight million USD are consulted/
interviewed. The professionals included 15
project managers, nine quantity surveyors,
five site engineers and one senior technical
officer of a waste management department/
unit. The interviews were on issues relating to
material waste and cost overruns at the post contract stage of a project. The collected data
were analysed manually, using the deductive
approach. This involves constant comparative
analysis of the data to generate common
patterns on material waste and cost overrun.
The research found that poor quality-of procurement management, construction
management, and site management would
cause material waste, which contributes
to project cost overruns. A good-quality
procurement management entails procuring
the appropriate materials, at the right time and
in accordance with specifications. Rework,
site accidents, inadequate site security/
fencing, poor site organisation and discipline, construction-site disputes, lack of experience, and lack of co-ordination among
the parties all contribute to material waste and cost overruns.
It can be concluded that proper attention to material waste issues has the
potential to minimise the rate of cost overrun at the post-contract stage of a
project. It is recommended that careful attention should be paid to the issues
identified in this study, as they would help reduce the rate of material waste and
cost overrun for projects.