An investigation into cost overruns for ongoing building projects in Abuja, Nigeria
Loading...
Date
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
Acta Structilia 2017
DOI
Abstract
The total amount of cost overruns for any
construction project can be fully determined
once the project is completed. Estimating the
amount of cost overruns at different stages of
ongoing construction projects is important for
project success. There is, however, a dearth of
research for this exercise. This article reports the
results of an investigative study on cost overruns
for ongoing building projects in Abuja. The
quantitative technique was adopted in this study.
The investigation included ongoing building construction projects within Abuja, from which
a sample of 30 building projects (public and
private) was purposively selected (project value
of ZAR100 million and above). The data were
sourced from the archival records (drawings,
bills of quantities, project progress reports, and
specifications) on the issues relating to the costs
and duration of building projects. The data were
analysed using descriptive (percentages) and
inferential methods. The results revealed that
the percentage of cost overruns ranged from a
minimum of 5.56% with 90% project completion,
and within 88% of the estimated time limit, to
a maximum of 216.08% with merely 5% project
completion, and within 8.3% of the estimated
time limit. The entire projects had average
cost overruns of 44.46%, with an average
project completion of 52.4%, and within 91.4%
of the average estimated time limit. Based
on these findings, it can be concluded that
continuous investigation into, and analyses
of cost overruns at stages of building projects
would encourage professionals to apply the
best mitigation measures, in order to achieve
a significant reduction in the total cost overrun
at the completion of a project. Construction
professionals should be well informed of these
consequences (cost overruns) at an early stage,
in order to evaluate the extent to which these
consequences could be minimised.