A Study of the Productivity of Permanent Staff and Contract Staff for POP Workers and Tilers in Abuja
Loading...
Date
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
School of Environmental Technology International Conference
DOI
Abstract
Every country's GDP is greatly impacted by the construction industry (CI). However, concerns have been raised
about the low productivity of the construction labor force during both the building and maintenance phases.
Construction project’s objectives could not be achieved unless labor productivity is raised. The aim of this
research work is to study the productivity of Plaster of Paris (POP) workers and tilers for both permanent and
contract staff within Abuja in other to advice appropriately the best staffing methods for such craft. Quantitative
research methodology was applied with the use of time study to study the productivity of tilers and POP workers
for both permanent and contract staff in 10 building sites in Abuja (5 sites for POP workers 5 for tilers). A total
of 20 gang was studied for the purpose of this study. Each gang is made of two members. The results were analyzed
using a simple arithmetic equation for calculating productivity. The results show mean productivity of the
permanent staff POP workers is 1.108hrs/m2 why that of the contract staff POP workers is 0.945hrs/m2
. The mean
productivity of the permanent staff tiler is 1.043hrs/m2 why that of the contract staff tiler is 0.871hrs/m2
. This
implies that the productivity of contract staffs for both POP workers and tilers are better than that of their
permanent staff counterparts. Contract staff is therefore advised for both POP activities and tilling activities in
Abuja but this must be done without exploitation of the workers.
Description
Keywords
Citation
Agada, D.I. and Ayegba, C., (2023)