Estimating Cost of Earthwork Using Computerized Visual Display Approach
Loading...
Date
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
DOI
Abstract
Removing and filling of earth materials to achieve the desired formation level is one of the
principal tasks in any road construction project. These activities involve significant cost of
excavating, hauling and placing of earth materials at a suitable place along the designed route.
This research is aimed at developing a Computerized Visual Display Approach that allows
earthwork cost to be estimated from a mass haul diagram. About 1.5km length of route was
selected within FUT-Minna main campus. The field observation was carried out using Total
Station (Hi-Target Total Station), the data were processed majorly using AutoCAD Civil and
Visual Basic (VB.net) was used in developing a computer program that allows earthwork cost to
be estimated from mass haul diagram. The result indicated that the road has two curves of very
larger radius (locating between chainage 00+00 and 00+400 while the other one is located
between chainage 01+150 and 01+525). The maximum point on the mass haul diagram was at
chainage 650m with computed volume and estimated cost of 79928.83m3 and 159857.67USD
while the minimum point on the mass haul diagram was at chainage 900m with computed
volume and estimated cost of 109620.83m3 and 219241.67USD, respectively. Also, the cumulated
volume of cut and fill along the route were +9544.50m3 and -1573.86m3 respectively and
earthwork cost at any given volume can be predicted using Earthwork Cost Prediction Graph
(ECPG). It was recommended that the developed software should be subjected to intensive
modifications that allows creation of comprehensive database of the estimated cost and be made
public for global criticisms and value addition.