Optimized Operation of Kainji Reservoir
Loading...
Date
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
AU Journal of Technology
DOI
Abstract
Niger River is the third largest river in Africa and it is impounded in Nigeria at
Kainji and Jebba for the sole purpose of generating electricity. Kainji Reservoir has a
capacity of generating 760 mW of electricity, while Jebba Reservoir which is 100 km
downstream of Kainji Reservoir, has a capacity of generating 540 mW. Flooding of the
plain downstream of the reservoirs is an annual phenomenon, especially in September.
On the other hand, water level in the reservoirs is low between March and May
resulting in low head for generating electricity. This study determines an operation
policy for Kainji Reservoir using Stochastic Dynamic Programming. The policy was
compared with the operation rules between 1996 and 1999. Inter-annual variation in
inflow to Kainji Reservoir was attributed to flow in September when peak rainfall
occurs in the catchment area that lies within Nigeria. The operation rules adopted by
Managers between 1996 and 1999 could not handle instantaneous high inflow between
August and September because the water level in the reservoir was high prior to the
arrival of such flow. Thus, there was high spillage so as to avoid structural failure of
the dam. It was also observed that volume of water released from the reservoir
remained high after the cessation of high inflow. It is recommended that the managers
should adopt an operation policy that could handle inter-annual variation in inflow to
the reservoir so as to maximize the benefit of impounding the water of River Niger and
also minimize the annual flooding of the river plain.