Purpose – Construction process is complex and traditionally fragmented; thus, it is almost impossible
to have a project completed without changes to the original plan or the construction process. The
purpose of this study is to identify and examine the causes of variation orders, ascertain their effects and
establish the cost and time performance implication as a result of variation orders.
Design/methodology/approach – This study obtained information from 90 construction
stakeholders on 30 completed educational building projects to ascertain the causes and effects of
variation orders on project delivery using questionnaire survey. In addition to this, a pro forma
document was designed to obtain the project characteristics, cost and time data from these 30 completed
educational building projects. Factor analysis was used to categorise the causes of variation orders,
while severity index was used to examine their effects on project delivery. The hypothesised statement
was tested using paired t-statistics to examine whether a statistically significant difference existed
between variation orders, cost and time performance of the projects.
Findings – The study identified 13 main factors as causes of variation orders and the results revealed
that the most frequent effects of variations were increase in construction costs, time, client
dissatisfaction, increase construction project rework and demolition and project abandonment. The results also showed that variation orders had significant effects on both cost and scheduled
performance of the educational building projects with average cost and time escalation of 33.95 and
29.45 per cent of the original project cost and time, respectively, for the entire projects studied, while average cost implication of variation orders is 23.79 per cent.
Practical implications – The findings in this study will be of assistance to government agencies
and management of public works in higher institutions of learning in managing variations in
construction projects. The study will also add to the current literature on the impact of variation
orders on educational building projects in developing countries. Finally, it will create the
much-needed awareness on the severity and implication of change or variation orders on project
delivery.
Originality/value – The study identified and examined the causes of variation orders, ascertained
their effects and established the cost and time effects of the causes of variation order on project performance. This will assist project initiators, contractors, consultants and other stakeholders to fully appreciate and understand the significant effects of variation orders on project performance.