INFLUENCE OF SELECTED PROCUREMENT METHODS ON DELIVERY OF COMMERCIAL BUILDING PROJECTS IN ABUJA, NIGERIA
Loading...
Date
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
DOI
Abstract
Project construction in Nigeria is faced with time and cost overrun as a result of the use
of wrong procurement methods. The last decade has exposed the declining level of
clients’ satisfaction in construction projects. This is as a result of perennial problems of
time and cost overruns in addition to the poor quality performance in the Nigerian
construction industry. Procurement methods differ from each other in term of allocation
of responsibilities, activities sequencing, process and procedure and organizational
approach in project delivery. It is therefore imperative to evaluate the influence of
procurement methods on the delivery of projects in Abuja, Nigeria. This research
assessed the factors influencing the various procurement methods in the delivery of
commercial building projects in Abuja with a view to choosing the appropriate
procurement method hence improving delivery quality of commercial building projects.
Data was collected using well-structured questionnaire. Analysis of data was carried out
using Relative Importance Index (RII), Mean Item Score (MIS) and One-way ANOVA.
Findings revealed that of the five (5) methods of procurement are frequently used in
commercial building construction in Abuja, the design & build system is the most used
(RII = 0.79); followed by the Traditional Procurement system (RII = 0.77); then the
Public Private Partnership (RII = 0.75) and Management Contracting (0.74); and
Direct Labour system is the least frequently used (RII = 0.70). The study also revealed
that the strategies for improving the cost (MIS = 3.95), quality (MIS = 3.75) and time
(3.67) delivery of commercial building projects in Abuja are effective. It was therefore
concluded that the Traditional, Management Contracting and Design & Build
procurement systems have significant impact on the delivery of construction projects in
Abuja. The study recommended that professionals should properly advise clients to use
the appropriate procurement method for the execution of commercial building projects
in order to avoid problem with time, cost and quality associated with the project