Environmental Impact Assessment of a Small Hydropower Plant: A Case Study of Orle River Auchi
Loading...
Date
Journal Title
Journal ISSN
Volume Title
Publisher
Nigerian Journal of Engineering Science Research
DOI
Abstract
An Environmental Impact Assessment (EIA) that identifies both the positive and
negative environmental impacts of some significant development at the planning stage of the
project is required statutorily in Nigeria in line with the provision of the Environmental Impact
Assessment bill of 2017. The study carried out an environmental impact assessment on a Small
Hydropower (SHP) in the Orle Valley, Auchi, Edo State. Screening and scoping processes were
carried out to interact with the competent authorities, stakeholders in the community, and
members of the public on the likely impacts of the project. A field survey was used to enumerate
the facilities and assets in the study area. The consequence of the hydropower plant construction,
operation, flooding and failure on humans, assets, use of water, and economic activities
associated with the river were analyzed. The safety by design approach was used to enhance the
design and operation of the reservoir to minimize the risk of its failure and disruption of
economic and social activities in the affected area. The result of the study indicates a low-level
risk and impact of the dam construction and operation on humans, assets, and ecosystems in
the vicinity of the reservoir and downstream of the river. It was observed that the economic
benefits of the dam will largely offset the aggregate cost of assets that will be consumed by the
plant construction and operation. The research work established a template for the determination
of EIA for small hydropower plant in developing countries.
Description
well pubished
Citation
1