A Bespoke Approach for Relating Material Waste to Cost Overrun in the Construction Industry
Loading...
Date
Journal Title
Journal ISSN
Volume Title
Publisher
Journal of Construction Business and Management
DOI
Abstract
The problems of material waste and cost overruns are common in the construction industry. These problems occur at different
stages of a construction project, from planning, design to project execution. The argument on how to eliminate cost overruns
has been on-going for the past 70 years as on-site wastage of materials leads to increase in the final project cost. This paper
examines the relationship between the causes of material waste and those of cost overrun at the pre-contract and post-contract
stages of a project. Literature review revealed that all (100%) the causative factors for material waste at the pre-contract and
post-contract stages of a project are linked to 96.88% and 81.36% of the causes of cost overruns at these stages respectively.
The results were further validated by interviews conducted with 30 construction professionals using purposive sampling
method within Abuja, Nigeria. Other causes of cost overruns which are not related to those of material waste are mostly the
micro-economic and macro-economic factors. It was also found that to achieve Effective Construction Material Waste
Management (ECMWM) for any construction project, the causes of material waste must be controlled at its sources and
causes, and at different stages of a project. The implication of these findings is that project cost overrun can be effectively
controlled by curbing the causes of material waste.